Cancelled
Tesla missed its December 2017 target of ~20,000 Model 3s per month (5,000/week); it built only about 793 in the final week of 2017. The 5,000-per-week rate was first reached in the last week of June 2018 (5,031 units), roughly six months after the original deadline. Green Car Reports ↗
In a July 2017 tweet, Musk wrote, 'Looks like we can reach 20,000 Model 3 cars per month in Dec' — about 5,000 cars per week. Actual December 2017 output ran at roughly 202 cars per week. Tesla eventually hit the 5,000-per-week rate in July 2018, about seven months late, making this one delivered late.
Cancelled
Delivered · Late
MissedComment on predictions and back the project. We email you a one-tap sign-in link — no password to remember.